Project Scope Statement Template
Project Scope Statement Sample Partially Completed Template
Download the Microsoft Word version
|
Project Name: |
Employee Portal
|
Project Number:
|
EEPO 0010
|
Project Manager:
|
Alice Johnston
|
Date:
|
May 4, 20xx
|
Business case
|
As the company grows, the number of individuals working virtually has
increased to over 150 in the past year and a half. Additionally,
virtual workers may only come into the office on average twice a
month for meetings with others. Access is needed to employee paperwork,
forms, and other documentation, along with the ability to
communicate and share information between employee and manager.
|
Objectives
|
Develop an employee portal to:
- Access various HR forms and other documentation relevant to the organization
- Provide a way to share information between employee and manager
- Provide a forum for employees to share information and communicate with each other
- Access to training/development plans and progress against those plans
- Access to performance review information
|
Scope description
|
The employee portal should be developed using
technology already in use within the company – Microsoft SharePoint.
The portal in phase 1 should provide access to all employees, but be
segmented depending on employee role within the organization.
The portal should provide access to the information documented above
in the “Objectives” section.
|
Acceptance criteria
|
Phase 1 of project is complete when portal contains the components
noted above and access has been provided to all employees, with access
level dependent on employee role.
|
Deliverables
|
Microsoft SharePoint portal for use by all company employees.
|
Exclusions
|
Any additional components of the portal are out of scope for this
project, but will be included in a list of objectives for Phase 2 of
project, to be completed within 1 year of rollout of Phase 1.
|
Constraints
|
Application development resources are currently involved in the roll
out of 2 other initiatives and will not be able to devote 100% of
time to this project until after 4 – 6 months of the start.
|
Assumptions
|
Application development resources are well versed in Microsoft SharePoint.
The use of Microsoft SharePoint as a portal can meet the
objectives of the organization, and allow for growth in the future.
|
Milestones
|
Date
|
Requirements gathering
|
June
|
Phase 1 development
|
July – Sept
|
Phase 1 testing
|
October
|
Phase 1 complete
|
November
|
Pilot group rollout
|
Dec – Feb
|
Incorporate changes/recommendations of pilot group
|
Feb – March
|
Organization wide rollout
|
March – April
|
Training in application
|
March – April
|
Project Budget
|
|
Estimated at $75,000 – $150,000 |
Project Risks
|
Training offshore team
|